Why this matters

The powerlink project would further impact ratepayers in a region with some of the nation’s highest utility rates.

Opponents of San Diego Gas and Electric’s plan to build a high-voltage power line across sensitive habitats and along several neighborhoods from Imperial to San Diego counties have taken their fight to court. 

Lawyers for two nonprofit corporations and 21 people allege a conspiracy and unlawful business practices added more than half a billion dollars to the cost of a controversial project that may send some of the nation’s highest electricity rates soaring even more.

Attorneys for Aguirre & Severson LLP of San Diego and DeBlase Brown Eyerly LLP of Los Angeles filed the lawsuit last week against SDG&E and the California Independent System Operator. The suit claims that the privately-owned utility broke state antitrust and unfair competition laws to become the builder of the Golden Pacific Powerlink, which would span more than 150 miles and be one of its largest-ever projects.

“Defendants’ conspiracy to allocate market share to SDG&E and resulting higher project costs are an affront to state and federal antitrust regulatory efforts in transmission markets,” the lawsuit reads.

A spokesperson for the state regulators at CAISO said the agency doesn’t comment on pending litigation. An SDG&E spokesperson said, “SDG&E has not been formally served with the complaint and is not in a position to comment on the matter at this time.”

The line would cut through Grapevine Canyon, a delicate wilderness area in Anza Borrego State Park, and past residential communities along the way to a new substation near San Onofre, bringing power to communities in Orange County. 

It has drawn opposition from residents across the region and  Borrego Community Development Corp. and the Anza-Borrego Foundation, the lead plaintiffs in the suit.

“We’ll see where this goes, but we just don’t want this line, no matter what,” said Jaime Purinton, the Anza-Borrego Foundation’s communications director. 

A view of Grapevine Canyon, Anza-Borrego Desert State Park on Aug. 9, 2026. (Philip Salata/inewsource)

The 20-page lawsuit details how SDG&E originally lost a competitive bid for the project to a company named Horizon West Transmission LLC. The suit lays out the math plainly: “Horizon West’s base capital cost was far less than that of its competitors: $1.004 billion for both the 500 kV Line and Substation. In contrast, private monopolist SDG&E stated a capital cost of $1.62 billion to build only the 500 kV Line.”

The suit says on or about Aug. 29, 2025, Horizon West, which is not a defendant in the lawsuit, “entered into an agreement, combination, or conspiracy” with SDG&E and CAISO to change the project. 

It says the three agreed SDG&E would “finance, construct, own, operate, and maintain” the 500-kilovolt line and Horizon West would “finance, construct, own, operate, and maintain” the substation.

The bidding process was instituted by state regulators in order to create more competition in the market and to protect public funds.

The estimated current cost of the project has left engineer and energy activist Bill Powers, one of the plaintiffs in the suit, scratching his head.

“Why would you win your absolute plum and then turn around and hand it to the incumbent?” he asked.

The lawsuit describes how state regulators selected Horizon West Transmission through comparative analysis, and how the company agreed to several cost caps. It says SDG&E’s losing proposal would cost 60 percent more. Yet SDG&E is involved.

“Its earlier bid for the project had already been rejected by the quasi-regulatory agency which commissioned the project in favor of a bid from a more cost-conscious, more experienced company,” the lawsuit reads. “SDG&E is alleged herein to have wielded its monopolistic market power to nonetheless take over the project.”

The lawsuit also outlines how customers would absorb the costs associated with the powerline at a time when anger over rising electricity prices and generally growing utility profits consistently rattle the region.

Powers told inewsource he believes that the lawsuit’s allegations, along with a drastically different picture of power needs than when the project was deemed necessary in 2023, make the case for halting it and reassessing what’s needed now.

He said rooftop solar is rejected as an option because of higher costs, but that it is more affordable if you factor in the cost of building massive power lines.

He called solar panels “a simple, elegant solution” but said utilities are threatened by it and “it’s just become an existential nationwide fight to kneecap rooftop solar and double down on the need for transmission.”

Sunrise over Borrego Springs on Aug. 9, 2026. (Philip Salata/inewsource)

In related news, SDG&E has adjusted its preferred route to bypass the city of Temecula, following months of pushback from city officials and residents there. 

The company’s preferred route still cuts through Anza-Borrego Desert State Park, a concern for critics worried about environmental dangers.

A spokesperson for SDG&E issued the following statement to inewsource when asked about the project’s route. 

“The Golden Pacific Powerlink is a state-identified project to strengthen the regional grid and support California’s energy goals,” it said. “Over the past year, SDG&E has studied a preliminary route and several alternative routes and engaged with communities along the way. Based on what we learned, we plan to propose the South Mountain Route in our application to the California Public Utilities Commission by the end of this year.

“This route has the potential to minimize certain environmental impacts and address engineering challenges. Route refinement is a normal part of project planning and no final route has been approved. The CPUC will make that decision following a public environmental review.”

The city of Temecula said in a press release last week that it was “encouraged” and “heartened” by the change, but it reiterated its commitment to ensuring the project never crosses through the city under any scenario.

Award-winning, community-centered investigative news costs resources, time and money. Help us continue this vital work.

Philip Salata is an investigative reporter and multimedia journalist covering the environment, energy and public health in San Diego and Imperial counties. He joined us in 2023. His work focuses on community impacts of the push toward the green economy and social/cultural issues in the border region...